Timeline for Forest Lake Restoration Project

The below timeline outlines the timing of the Forest Lake spillway restoration project. Please visit our events page for more information on upcoming meetings.


  1. Amend Lake Level Order - Completed

  2. Finalize Engineering of Dam Improvement Project - Completed

  3. Site Cleanup and Stream Restoration - ongoing; complete by April 2024

  4. Finalize Special Assessment Roll and Computation of Costs - ongoing

  5. Finalize Construction Contract - March 2024

  6. Special Assessment Hearing - April 11, 2024

  7. County Board Approval of Assessments and Costs - April/May 2024 (April 23)

  8. Prepayments - April/May 2024 (May 14)

  9. Financing - May/June 2024

  10. Construction - May/June 2024


Items 7-10 have tentative dates subject to approval of / coordination with bond counsel.