The below timeline outlines the timing of the Forest Lake spillway restoration project. Please visit our events page for more information on upcoming meetings.
Amend Lake Level Order - Completed
Finalize Engineering of Dam Improvement Project - Completed
Site Cleanup and Stream Restoration - ongoing; complete by April 2024
Finalize Special Assessment Roll and Computation of Costs - ongoing
Finalize Construction Contract - March 2024
Special Assessment Hearing - April 11, 2024
County Board Approval of Assessments and Costs - April/May 2024 (April 23)
Prepayments - April/May 2024 (May 14)
Financing - May/June 2024
Construction - May/June 2024
Items 7-10 have tentative dates subject to approval of / coordination with bond counsel.